Phase II of the Village street paving project schedule

Share this:

Weather permitting, residents in South I and West II will have new roads and curbing installed by early August.  Please note the “important reminders” below.

On or about March 27, work will begin on Phase II of the Village Street Paving Project. This work will start with pulverizing of the existing pavement – from there the crews will start removing the curb and gutter, driveway approaches, and any sidewalk replacements required.  After all demolition and removals are complete, the electrical contractor will install new wiring and conduit for all street lighting in the project areas.  After wires and conduits are installed, the curbing contractor will start preparing curb areas. 

Curb install preparation will include grading subbase and installing stringlines.   A curbing machine will place the concrete curbs.  Flatwork concrete crews will follow behind the curb machines and install driveway approaches and sidewalks.  **Remember do not walk, drive, or park on new concrete until given notice to do so.** 3-5 days after curbs are installed, crews will start landscaping up to and around all new concrete. 

After all concrete work is complete, asphalt contractors will begin fine grading the roadways in preparation for asphalt placement.  After the fine grading is done, asphalt crews will place a binder course of asphalt throughout the entire subdivision.  After completion of binder course, crews will install the final surface course of asphalt.  As required, additional landscaping and other incidental items will need to be cleaned up and finished. 

Below is a tentative schedule of the items listed above.  Note this schedule is tentative and very weather dependent.  The construction team will be meeting weekly to update this schedule and will post notifications as soon as possible.  The work listed above is a general overview of the process from start to finish and may not be all inclusive of the work being completed.  If you have specific questions, please call the Village DPW at 920.459.3881 with your concerns.

 

Schedule for West II:

Demolition and removals:

  • Green / Pine Tree Lane – March 27 – April 9
  • Hill St. – March 31 – April 15
  • West Park Lane – April 3 – April 20
  • Summit / Hawthorne – April 10 – April 30
  • Audubon – April 17 – May 7
  • Valley / School St. – April 24 – May 20

 

Electrical Work:

  • Green, Pine, Hill, Park, Summit – April 17 – May 7
  • Audubon, Valley, School – May 8 – May 28

 

Curb Work:

  • Green, Pine, Hill, Park, Summit – April 25 – May 21
  • Audubon, Valley, School – May 15 – June 11

 

Concrete Flatwork:

  • Green, Pine, Hill, Park, Summit – May 15 – June 11
  • Audubon, Valley, School – June 5 – July 2

 

Landscaping:

  • Green, Pine, Hill, Park, Summit – May 15 – June 18
  • Audubon, Valley, School – June 5 – July 10

 

Fine grading and asphalt install:

  • Green, Pine, Hill, Park, Summit – June 5 – July 10
  • Audubon, Valley, School – June 26 – July 30

 

Schedule for South I:

Demolition and removals:

  • Roosevelt East – March 27- April 9
  • Parkway (E. Riverside to Roosevelt) – March 31 – April 16
  • E. Riverside – March 31 – April 17
  • Center walk – April 10 – April 20
  • Roosevelt West – April 10 – April 30
  • Washington Walk / Square – April 16 – April 30
  • Lower Rd – April 17 – May 7
  • Center Ln – April 23 – May 8
  • Parkway (Riverside to Roosevelt) – April 24 – May 14
  • West Riverside – April 24 – May 14

 

Electrical Work:

  • Roosevelt East to East Riverside – April 10 – April 30
  • Roosevelt West to West Riverside – April 24 – May 21

 

Curb Work:

  • Roosevelt East to East Riverside – April 10 – May 7
  • Roosevelt West to West Riverside – May 1 – May 28

Concrete Flatwork:

  • Roosevelt East to East Riverside – May 1 – May 28
  • Roosevelt West to West Riverside – May 22– June 18

 

Landscaping:

  • Roosevelt East to East Riverside – May 1 – June 4
  • Roosevelt West to West Riverside – May 22 – June 25

 

Fine grading and asphalt install:

  • Roosevelt East to East Riverside – May 22 – June 25
  • Roosevelt West to West Riverside – June 12 – July 10

 

Important reminders:

  • Emergency access will be provided to all residents at all times.

  • Street lights will be out starting March 27 until Mid-May.

  • Temporary “No Parking” signs will be installed as required.

  • Existing driveways and entrances will be left with a small gravel or milled asphalt ramp to existing grade.  These ramps can wear out or wash away, use caution navigating any ramp or edge of pavement.  If in doubt, do not access this location and inform the village of any wash outs.  We will repair/replace as needed.  Crews will do their best to allow for access, however parking on adjacent streets or parking lot areas is appreciated.

  • Fresh concrete curb and flatwork shall not be walked on for 36 hours after installation, no vehicular traffic for 7 days after installation.  Damage incurred during this time will require additional preparation and closure time

  • Gravel and milled asphalt surfaces can be hazardous and drivers / pedestrians should slow down and use caution at all times on these surfaces.  These surfaces can also cause dust and stone chips to be displaced causing damage to vehicles.   SLOW DOWN!

  • Written notifications will be placed on the front doors of residences with anticipated dates that their driveways will be closed.  Anticipated closure duration will be listed on the notice.  During closures residents will be expected to find alternate parking locations, preferably on adjacent streets.

  • Garbage pickup will continue on schedule until otherwise notified.  As curb and flatwork progresses arrangements will be made for alternate garbage collection needs.